1: The PP/DOE are requested to list all the data and parameters to be monitored in line with applied methodology as per EB 48 Annex 60 paragraph 10 (a).
The landfill will received waste till year 2017. As per paragraph 8 of AMS III.G. version 6 the total amount of waste landfilled in a year and weight fraction of each waste type should be monitored.

2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
1. Average O&M cost in the period of investment analysis is calculated to be 1,874,250 RMB/yr, which is about 10% of total investment. The DOE states on page A139 of validation report that average annual O&M cost is only 1.5% of the total investment and hence it was considered as reasonable by DOE. DOE shall clearly state how O&M costs were assessed to be reasonable.