12:16 10 Oct 26
Info Report Check
Submission incomplete:
1: The DOE is requested to include description of the process taken to validate the accuracy and completeness of the project description in VR as per VVM v1.2 paragraph 64(a).
The PP/DOE is requested to provide i) technical specification and the ownership of the coal-fired steam boilers used in the absence of the project ii)operation date of three production lines.
2: The DOE is requested to describe how each applicability condition of the methodology/ies is fulfilled by the project activity as per VVM v1.2 paragraph 76.
The DOE is requested to validate the remaining lifetime of the coal-fired boilers according to the methodology
3: The DOE is requested to describe how it has validated the project boundary as per VVM v1.2 paragraph 80.
The PP/DOE is requested to clarify why the coal-fired steam boilers are not included in the project boundary.
4: The DOE is requested to confirm the accuracy of the financial calculations carried out for the investment analysis as per VVM v 1.2 paragraph 114 (c).
The DOE is requested to further validate the suitability of the steam price used in the investment analysis, in doing so, the DOE is requested to justify the internal contracted value is a market price.
1: The DOE is requested to include description of the process taken to validate the accuracy and completeness of the project description in VR as per VVM v1.2 paragraph 64(a).
The PP/DOE is requested to provide i) technical specification and the ownership of the coal-fired steam boilers used in the absence of the project ii)operation date of three production lines.
2: The DOE is requested to describe how each applicability condition of the methodology/ies is fulfilled by the project activity as per VVM v1.2 paragraph 76.
The DOE is requested to validate the remaining lifetime of the coal-fired boilers according to the methodology
3: The DOE is requested to describe how it has validated the project boundary as per VVM v1.2 paragraph 80.
The PP/DOE is requested to clarify why the coal-fired steam boilers are not included in the project boundary.
4: The DOE is requested to confirm the accuracy of the financial calculations carried out for the investment analysis as per VVM v 1.2 paragraph 114 (c).
The DOE is requested to further validate the suitability of the steam price used in the investment analysis, in doing so, the DOE is requested to justify the internal contracted value is a market price.