1: The DOE is requested to describe how each applicability condition of the methodology/ies is fulfilled by the project activity as per VVS version 2 paragraphs 76 and 77.
The DOE is requested to clarify how it considered that the project activity fulfils the applicability condition 3 as the information regarding the future natural gas power capacity addition has not been provided. Please refer to VVS para 76.
2: The DOE is requested to describe how it has validated the suitability of the input values used in the financial calculations as per VVS version 2 paragraphs 120 and 123 (a).
The DOE is requested to provide further information on how each input values used in the levelized cost analysis for each alternative has been crosschecked in line with VVS para 120(b) and (c) as the validation report does not provide any specific information.
1: The DOE is requested to describe how each applicability condition of the methodology/ies is fulfilled by the project activity as per VVS version 2 paragraphs 76 and 77.
The DOE is requested to clarify how it considered that the project activity fulfils the applicability condition 3 as the information regarding the future natural gas power capacity addition has not been provided. Please refer to VVS para 76.
2: The DOE is requested to describe how it has validated the suitability of the input values used in the financial calculations as per VVS version 2 paragraphs 120 and 123 (a).
The DOE is requested to provide further information on how each input values used in the levelized cost analysis for each alternative has been crosschecked in line with VVS para 120(b) and (c) as the validation report does not provide any specific information.