1: The DOE is requested to confirm the accuracy of the financial calculations carried out for the investment analysis as per VVM v 1.2 paragraph 114 (c).
The DOE is requested to confirm the accuracy of the calculations considering that the formulae used to calculate the levelized costs of producing lignite and biomass are different (see worksheet 'Levelised cost').

2: The DOE is requested to include information on how it has validated sensitivity analysis of the investment analysis as per VVM v1.2 paragraph 111 (e).
The DOE is to determine under what conditions variations in the result of the investment analysis would occur, and the likelihood of those conditions.