Info Report Check
Submission incomplete:
The PP/DOE are requested to list all the data and parameters to be monitored in line with applied methodology as per EB 48 Annex 60 paragraph 10 (a).
According to the validated PDD (page 27), the PP is using a number of monitored parameters to calculate the quantity of net electricity supplied to the grid instead of directly metering the net electricity supplied to the grid. The PP/DOE must list each of the required parameters in section B.7.1 in the PDD together with the relevant monitoring requirements. Information regarding the ownership of the metering system e.g. whether this is under the PP or grid company control, shall be clearly presented. Furthermore, it is advisable to present a schematic diagram to illustrate the relationship and boundary between the proposed CDM project and "the turbines from other wind farm developers at the project site".