Submission incomplete:
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In particular the DOE is requested to transparently report the list of projects used to crosscheck the suitability of the benchmark, investment cost and O&M cost of the proposed project, given that a different number of CDM registered similar activities in Vietnam was used in each case (i.e. 25 projects are listed to crosscheck the benchmark, 38 projects are considered to crosscheck the total investment cost, and 52 projects are used to crosscheck the O&M cost).
2: The DOE is requested to include information on how it has validated sensitivity analysis of the investment analysis as per VVM v1.2 paragraph 111 (e).
The DOE should include a validation opinion on the variations in the total investment costs, O&M costs, power tariff, and operational hours (PLF) that would make the IRR of the project reach the benchmark and the likelihood of these conditions.
3: The DOE is requested to address the changes made to the project deign since the global stakeholder consultation was conducted as per VVM v1.2 paragraph 173(c).
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In particular the DOE is requested to transparently report the list of projects used to crosscheck the suitability of the benchmark, investment cost and O&M cost of the proposed project, given that a different number of CDM registered similar activities in Vietnam was used in each case (i.e. 25 projects are listed to crosscheck the benchmark, 38 projects are considered to crosscheck the total investment cost, and 52 projects are used to crosscheck the O&M cost).
2: The DOE is requested to include information on how it has validated sensitivity analysis of the investment analysis as per VVM v1.2 paragraph 111 (e).
The DOE should include a validation opinion on the variations in the total investment costs, O&M costs, power tariff, and operational hours (PLF) that would make the IRR of the project reach the benchmark and the likelihood of these conditions.
3: The DOE is requested to address the changes made to the project deign since the global stakeholder consultation was conducted as per VVM v1.2 paragraph 173(c).