1: The PP/DOE are requested to explain in the PDD the methodological choices for the calculation of the baseline, project emissions, leakage and emission reductions as per PS version 1 paragraphs 50 and 51.
The information regarding the applicability of paragraph 10 (f), para 16 and 17 of the Tool to calculate the Emission Factor for an electricity systerm, Version 4 is not provided in the PDD. This is with reference to the grid EF being calculated using the China South China Power Grid.

2: The DOE is requested to describe how each applicability condition of the methodology/ies is fulfilled by the project activity as per VVS version 2 paragraphs 76 and 77.
The DOE is requested to provide information on how it has validated the the applicability of paragraph 10 (f), para 16 and 17 of the Tool to calculate the Emission Factor for an electricity system, Version 4 for the project activity. This is with reference to the grid EF being calculated using the China South China Power Grid.