07:11 08 Jun 25
Info Report Check
Submission incomplete:
1: The The PP/DOE are requested to list all the data and parameters to be monitored in line with applied methodology as per EB 48 Annex 60 paragraph 10 (a).
The PP/DOE are requested to clarify if the fossil fuel consumption of the baseline boilers is included in the monitoring plan.
2: The DOE is requested to provide a statement whether the identified boundary, sources and gases are justified for the project activity as per VVM v1.2 paragraph 80.
The DOE has not clarified whether the two fossil fuel boilers are included in the project boundary.
3: The DOE is requested to describe the steps taken to assess the equations applied to calculate the baseline/ project emissions, leakage and emission reductions as per the chosen methodology as per VVM v1.2 paragraph 92.
The DOE has not described how project emissions resulting from the possible operation of the fossil fuel boilers would be accounted for.
1: The The PP/DOE are requested to list all the data and parameters to be monitored in line with applied methodology as per EB 48 Annex 60 paragraph 10 (a).
The PP/DOE are requested to clarify if the fossil fuel consumption of the baseline boilers is included in the monitoring plan.
2: The DOE is requested to provide a statement whether the identified boundary, sources and gases are justified for the project activity as per VVM v1.2 paragraph 80.
The DOE has not clarified whether the two fossil fuel boilers are included in the project boundary.
3: The DOE is requested to describe the steps taken to assess the equations applied to calculate the baseline/ project emissions, leakage and emission reductions as per the chosen methodology as per VVM v1.2 paragraph 92.
The DOE has not described how project emissions resulting from the possible operation of the fossil fuel boilers would be accounted for.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: