Info Report Check
Submission incomplete:
1: The PP/DOE are requested to list all the data and parameters to be monitored in line with applied methodology as per EB 48 Annex 60 paragraph 10 (a).
Please explain whether the parameter TEGy should be monitored as part of the monitoring plan

2: The DOE is requested to state whether the data and parameters are conservative and appropriate if they are fixed ex-ante (not need to monitor) during the project activity crediting period as per VVM v1.2 paragraph 91.
In particular, the emission factor of SIC grid given that the emission factor applied in the project activity is about 60% higher than the emission factor applied in another project (reference number 1374) which is connected to the same grid as the project activity.

3: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v1.2 , paragraph 111(b).
In particular, the electromechanical equipment costs, civil works costs, engineering and supervision costs and transmission line costs which are listed in page 14 of the validation report. Further, the DOE shall explain why the acquisition costs has been included as part of the investment cost.