Submission incomplete:
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In doing so, please report further on how it has validated: a) the investment costs based on a proposal considering that purchase agreements were available before the investment decision which are the project starting dates (25/06/2009 and 24/10/2009); and b) the crosschecking of the investment and O&M costs considering that different sets of "similar projects" were used to assess these two input values.

2: The DOE is requested to provide information on how it has validated the suitability of the benchmark as per VVM v 1.2 paragraph 114 (b).
In particular, the DOE is requested to provide the date for the following values used for the benchmark calculation for sub-project 1: a) risk free rate of return; and b) beta value.

3: The DOE is requested to include a list of interviewees and document reviewed as per VVM v1.2 paragraph 174 (d).
There are multiple number of documents with the same reference number (validation report pages 42-45). Due to this, the reference provided in the document cannot be identified. Please provide unique identification for each reference document.