Info Report Check
Submission incomplete:
1: The DOE is requested to provide the information about the greenhouse gas emissions within the project boundary caused by the implementation of the project activity which contribute to more than 1% of the expected annual emission reductions ER/year and which are not addressed in by the applied methodology as per VVM v1.2 paragraph 77.
The DOE has not provided information about the greenhouse gas emissions within the project boundary caused by the implementation of the project activity which contribute to more than 1% of the expected annual emission reductions ER/year and which are not addressed in by the applied methodology as per VVM v1.2 paragraph 77.

2: The DOE is requested to provide a description of steps taken to cross-check the information given in the PDD as per VVM v1.2 paragraph 88.
Issue 1: The PDD, page 48 indicates that "there is an excess of 25% more waste available than needed for the Project, so there is no leakage amount to be considered for this Project." However, the DOE has not provided information on how it assessed that the quantity of available biomass in the region (e.g., 50 km radius), is at least 25% larger than the quantity of biomass that is utilised including the project activity, as per EB 47 Annex 28, paragraph 18.

Issue 2: The PDD, page 5 states that "the objectives of the project are to utilize the available biomass fuels (horticultural wastes) generated by landscaping companies in Singapore. This waste is currently landfilled or incinerated." However, the validation report does not contain information on how the DOE assessed that the biomass is currently landfilled or incinerated.