Info Report Check
Submission incomplete:
1: The PP/DOE are requested to describe that CDM was seriously considered in the decision to proceed with the project activity as per EB 48 Annex 60 paragraph 10 (a).
Prior consideration of CER revenues has not been demonstrated in the PDD.

2: The PP/DOE are requested to describe the continuing and real actions taken to achieve CDM status for the project activity as per EB 48 Annex 60 paragraph 10 (a).
The timeline of events has not been given in the PDD to check if continuous and real actions have been taken in parallel with the project implementation to secure carbon revenues.

3: The PP/DOE are requested to list all relevant assumptions, data, input values and references used in the investment analysis and the results of the investment analysis as per EB 48 Annex 60 paragraph 10 (a).
The input values used in conducting the financial analysis has not been detailed in the PDD.

4: The PP/DOE are requested to indicate the project starting date in the PDD as per EB 48 Annex 60 paragraph 10 (a).