1: The PP/DOE are requested to describe in detail the monitoring plan as per EB 48 Annex 60 paragraph 10 (a).
The PP/DOE are requested to clarify the monitoring plan: the PDD mentions the presence of several turbines in the monitoring section (page 35) while only one turbine is indicated in the technology description (page 7).

2: The DOE is requested to provide information on the PPs' ability to implement the monitoring plan as per VVM v1.2 paragraph 124(c).
The DOE has not described how the project participant will monitor the use of captive electricity or how the electricity imported by the project activity will be accounted for.