Info Report Check
Submission incomplete:
1: The PP/DOE are requested to complete all the PDD sections for the description of the project activity as per EB 48 Annex 60 paragraph 10 (a).
The total installed capacity of the project is based on rated turbine capacity as 1.5 x 8 = 12.0 MW. As per footnote 6 of General Guidelines to the SSC CDM methodologies, version 16 the total installed capacity for renewable electricity generation projects should be based on rated generator capacity which is 1.540 MW for this project. The DOE is requested to clarify whether the installed capacity for the project activity is in line with the fore mentioned guideline.

2: The DOE is requested to include validation opinion on the accuracy and completeness of the project description in the validation report as per VVM v1.2 paragraph 64(b).


3: The DOE is requested to describe how it has validated that the selected monitoring methodology(ies) are correctly applied and they are not subject to clarifications, revisions or deviations as per VVM v1.2, paragraphs 72-74.
The DOE should clarify how export and import of electricity measured by meters M1 and M2 as shown on page 26 of the PDD will be cross checked with invoices for sale of electricity to the grid because invoices will be issued based on meter reading at substation that will measure net electricity for old and expansion project together.