1: The DOE is requested to state if all the documents/data used in the PDD for the emission reduction calculations are correctly quoted and interpreted in the PDD as per VVM v1.2 paragraph 92(b).
The VR lacks information on how the DOE has validated the leakage from transportation of raw material and biomass being likely to be smaller than 10%.
2: The DOE is requested to provide information on the steps taken to validate the project starting date as per VVM v 1.2 paragraph 104 (a).
The VR lacks information on how the DOE validated the selected start date being the earliest date at which either the implementation or construction or real action of a project activity begins. The date of the Purchase Order of major equipment is missing.
3: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
(a) The VR has not provided information on how the following input values have been validated in line with the VVM version 01.2 paragraph 111b: (i) Specific Energy Consumption (16001.05 MJ/MWh) for both coal and biomass; (ii) NCV of biomass and NCV of coal; (iii) the annual coal price escalation indicated in the spreadsheet; and
(b)The VR lacks information on how the input values sourced from DPR were applicable at the time of the investment decision in line with EB51 Annex 55 paragraph 6, given that there is no information with regards to the completion of the DPR.
1: The DOE is requested to state if all the documents/data used in the PDD for the emission reduction calculations are correctly quoted and interpreted in the PDD as per VVM v1.2 paragraph 92(b).
The VR lacks information on how the DOE has validated the leakage from transportation of raw material and biomass being likely to be smaller than 10%.
2: The DOE is requested to provide information on the steps taken to validate the project starting date as per VVM v 1.2 paragraph 104 (a).
The VR lacks information on how the DOE validated the selected start date being the earliest date at which either the implementation or construction or real action of a project activity begins. The date of the Purchase Order of major equipment is missing.
3: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
(a) The VR has not provided information on how the following input values have been validated in line with the VVM version 01.2 paragraph 111b: (i) Specific Energy Consumption (16001.05 MJ/MWh) for both coal and biomass; (ii) NCV of biomass and NCV of coal; (iii) the annual coal price escalation indicated in the spreadsheet; and
(b)The VR lacks information on how the input values sourced from DPR were applicable at the time of the investment decision in line with EB51 Annex 55 paragraph 6, given that there is no information with regards to the completion of the DPR.