Submission incomplete:
1: The install capacities of the specific CPAs in this request for issuance are not consistently described. E.g. page 8 of the monitoring report mentions an installed capacity of 1.15 MW for CPA 9904-P1-0003-CP1 whereas page 14 of the verification report mentions an installed capacity of 1.06 MW for the same CPA. The DOE is requested to confirm the capacity for the stated CPA; in doing so, please refer to paragraph 19(d) of CDM VVS for PoA version 3.
2: Delayed calibration of electricity meters is observed in the CPAs during this monitoring period, thus a calibration error of 0.5% is applied for adjustment (i.e. as explained in page 22 of the verification report). However, the calibration results described on page 22 of the verification report indicate a different accuracy level (i.e. within an acceptable limit of +/- 2%) which are not consistent with the calibration error of 0.5% applied for adjustment. The DOE is requested to confirm the calibration error. In doing so, please refer to page 22 of the verification report and refer to paragraph 350 of CDM VVS for PoA version 3.
3: The formula applied in calculating the emission reductions is not in line with paragraph 15 of AMS I.D version 17, in particular for CPAs involving retrofit/capacity addition of existing hydropower plants (i.e. CPA 0008 and CPA 0009). Instead of applying paragraph 15 of AMS I.D version 17, those CPAs applied the formula in paragraph 16/18 of AMS I.D version 17. The DOE shall provide information on how it has verified that the emission reductions have been carried out in accordance with the applied methodology. Please refer to paragraph 357(c) of VVS for PoA version 3.
1: The install capacities of the specific CPAs in this request for issuance are not consistently described. E.g. page 8 of the monitoring report mentions an installed capacity of 1.15 MW for CPA 9904-P1-0003-CP1 whereas page 14 of the verification report mentions an installed capacity of 1.06 MW for the same CPA. The DOE is requested to confirm the capacity for the stated CPA; in doing so, please refer to paragraph 19(d) of CDM VVS for PoA version 3.
2: Delayed calibration of electricity meters is observed in the CPAs during this monitoring period, thus a calibration error of 0.5% is applied for adjustment (i.e. as explained in page 22 of the verification report). However, the calibration results described on page 22 of the verification report indicate a different accuracy level (i.e. within an acceptable limit of +/- 2%) which are not consistent with the calibration error of 0.5% applied for adjustment. The DOE is requested to confirm the calibration error. In doing so, please refer to page 22 of the verification report and refer to paragraph 350 of CDM VVS for PoA version 3.
3: The formula applied in calculating the emission reductions is not in line with paragraph 15 of AMS I.D version 17, in particular for CPAs involving retrofit/capacity addition of existing hydropower plants (i.e. CPA 0008 and CPA 0009). Instead of applying paragraph 15 of AMS I.D version 17, those CPAs applied the formula in paragraph 16/18 of AMS I.D version 17. The DOE shall provide information on how it has verified that the emission reductions have been carried out in accordance with the applied methodology. Please refer to paragraph 357(c) of VVS for PoA version 3.