Info Report Check
Submission incomplete:
1. In line with para 141-147 and para 168-171 of the CDM project cycle procedure for proramme of activities, only changes to the PoA-DD can be submitted under the issuance track. Changes to component project activities shall be done via notification of changes as per section 6.3 of the PCP. Thus, the notification of change is not permissible with the request for issuance.
2. Further we have observed that this issuance request contains applicable PRC for the Component project activiy. Therefore, until the PoA PRC and the CPA leve change request has not been approved by the board, this issuance request shall not be submitted.
3. There is an inconsistency of the version fo the PoA DD within the verification report as page 1,3 & 26 refer to PoA DD version 9 and page 3,11 & 26 to PoA DD version 8.
4. The validation report for post-registration changes for CPA 1 and CPA 2 refer to PoA DD version 9 dated 16/12/2018 which has not been approved yet.