Scope: The validation opinion does not contain an assessment on when the changes occurred, reasons for those changes taking place, whether the changes would have been known prior to registration of the project activity, and how the changes would impact the overall operation/ability of the project activity to deliver emission reductions as stated in the PDD (VVS v.7 para 325 (b))
Issue:
The DOE has not provided an assessment opinion on: (a) the reasons for those changes taking place; (b) whether the changes would have been known prior to registration of the project activity, since the decision to increase the capacity was made on 20/11/2012 prior to the request for registration (i.e. 24/12/2012); and (c) how the changes would impact the overall operation/ability of the project activity to deliver emission reductions, in particular when the increased five G-97 turbine started commission.