15:29 08 Jan 25
Info Report Check
Submission incomplete:
1: Scope: The verification report does not state that the monitoring plan is in accordance with the applied methodology. (VVS v.2 para 232)
Issue: The DOE is requested to further substantiate the compliance of the registered monitoring plan with the methodology as Section B.7.1 of the PDD states that the parameter EFgrid is fixed ex-ante while the methodology (page 12) states that if either option 1 (BM) or option 2 (CM) are selected, they will be estimated ex post, as described in “Tool to calculate the emission factor for an electricity system”.
2: Scope: The verification report does not provide a conclusion on the verified amount of emission reductions achieved and/or determine that calculations of baseline emissions, project emissions and leakage as appropriate have been carried out in accordance with the formulae and methods described in the monitoring plan and the applied methodology document. (VVS v2, para 246 (c), 284 (i))
Issue:The PP/DOE are requested to further substantiate how the calculation of the parameter EFBL,plant,y (Emission factor for the project activity power plant in the baseline) has been in accordance with the methodology (page 10, equation 9) which requires the application of the minimum between the EF based on the historical data and the EF based on the project activity data
1: Scope: The verification report does not state that the monitoring plan is in accordance with the applied methodology. (VVS v.2 para 232)
Issue: The DOE is requested to further substantiate the compliance of the registered monitoring plan with the methodology as Section B.7.1 of the PDD states that the parameter EFgrid is fixed ex-ante while the methodology (page 12) states that if either option 1 (BM) or option 2 (CM) are selected, they will be estimated ex post, as described in “Tool to calculate the emission factor for an electricity system”.
2: Scope: The verification report does not provide a conclusion on the verified amount of emission reductions achieved and/or determine that calculations of baseline emissions, project emissions and leakage as appropriate have been carried out in accordance with the formulae and methods described in the monitoring plan and the applied methodology document. (VVS v2, para 246 (c), 284 (i))
Issue:The PP/DOE are requested to further substantiate how the calculation of the parameter EFBL,plant,y (Emission factor for the project activity power plant in the baseline) has been in accordance with the methodology (page 10, equation 9) which requires the application of the minimum between the EF based on the historical data and the EF based on the project activity data
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: