Info Report Check
Submission incomplete:
1: Scope: The monitoring report does not contain the implementation status of the project (including a brief description of the installed technology and/or equipments, relevant dates of project activity e.g. date of construction, commissioning, continued operation periods, etc.) during the monitoring period under consideration. (EB48 - Annex 68 paragraph 10 (a) (i) & EB 54 Annex 34).
Issue: The PP/DOE shall address the inconsistency in the start of the operation of the project activity as the monitoring report (p. 6) indicates that the starting date of operation of the project activity was on 01/05/09 while the validation report (p. 15) mentions that phase I of the project activity was commissioned and operated on 29/11/08.
2: Scope: The monitoring report does not contain a description of the monitoring systems, quality assurance and/or quality control system employed by the project activity, data collection procedures (information flow including data generation, aggregation, recording, calculation and reporting), organizational structure, roles and responsibilities of personnel, emergency procedures for the monitoring system, and/or line diagrams showing all relevant monitoring points). (EB48 - Annex 68 paragraph 10 (a) (ii) & EB 54 Annex 34).
Issue: The PP/DOE shall indicate the monitoring points for the boiler feed water; clearly identifying water return loops from the dryer, heating station and steam turbine (please refer monitoring report; p. 8) to the boiler.
3: Scope: The monitoring report does not contain emission factors, IPCC default values, and/or other reference values used in the calculation of emission reductions. (EB48 - Annex 68 paragraph 10 (a) (v)).
Issue: The DOE shall correct the inconsistency in the referenced documents i.e. the No. of ISO tankers (NISO tanks) refers to P04-10 which addresses outage/breakdown, Net Calorific value of the mixed biomass (NCVbiomass) refers to P04-8 which addresses ISO tanks etc.
4: Scope: The verification report does not determine if the assumptions used in emission calculations have been justified and/or emission factors, default values and other reference values have been correctly applied. (VVM v.1.2 para 208 (d) & (e))
Issue: The PP/DOE shall:
i) clarify if the data used for baseline emission calculation is consistent with the start of the project operation considering that the date of the project activity is reported as 29/11/08 while the data is monitored from 18/11/2008,
ii) report how project emissions due to the onsite diesel oil- fired rotating dryers (monitoring report page 4) have been accounted for,
iii) report how it verified the availability of the surplus biomass (61 % for year 2008 and 58% for year 2009) as the provided link appears to give Government published data (year 2011) for the whole country and therefore not specific to the proposed project activity boundary, and
iv) report how emissions due to the transport of the biomass residues used by the project activity have been accounted for.
1: Scope: The monitoring report does not contain the implementation status of the project (including a brief description of the installed technology and/or equipments, relevant dates of project activity e.g. date of construction, commissioning, continued operation periods, etc.) during the monitoring period under consideration. (EB48 - Annex 68 paragraph 10 (a) (i) & EB 54 Annex 34).
Issue: The PP/DOE shall address the inconsistency in the start of the operation of the project activity as the monitoring report (p. 6) indicates that the starting date of operation of the project activity was on 01/05/09 while the validation report (p. 15) mentions that phase I of the project activity was commissioned and operated on 29/11/08.
2: Scope: The monitoring report does not contain a description of the monitoring systems, quality assurance and/or quality control system employed by the project activity, data collection procedures (information flow including data generation, aggregation, recording, calculation and reporting), organizational structure, roles and responsibilities of personnel, emergency procedures for the monitoring system, and/or line diagrams showing all relevant monitoring points). (EB48 - Annex 68 paragraph 10 (a) (ii) & EB 54 Annex 34).
Issue: The PP/DOE shall indicate the monitoring points for the boiler feed water; clearly identifying water return loops from the dryer, heating station and steam turbine (please refer monitoring report; p. 8) to the boiler.
3: Scope: The monitoring report does not contain emission factors, IPCC default values, and/or other reference values used in the calculation of emission reductions. (EB48 - Annex 68 paragraph 10 (a) (v)).
Issue: The DOE shall correct the inconsistency in the referenced documents i.e. the No. of ISO tankers (NISO tanks) refers to P04-10 which addresses outage/breakdown, Net Calorific value of the mixed biomass (NCVbiomass) refers to P04-8 which addresses ISO tanks etc.
4: Scope: The verification report does not determine if the assumptions used in emission calculations have been justified and/or emission factors, default values and other reference values have been correctly applied. (VVM v.1.2 para 208 (d) & (e))
Issue: The PP/DOE shall:
i) clarify if the data used for baseline emission calculation is consistent with the start of the project operation considering that the date of the project activity is reported as 29/11/08 while the data is monitored from 18/11/2008,
ii) report how project emissions due to the onsite diesel oil- fired rotating dryers (monitoring report page 4) have been accounted for,
iii) report how it verified the availability of the surplus biomass (61 % for year 2008 and 58% for year 2009) as the provided link appears to give Government published data (year 2011) for the whole country and therefore not specific to the proposed project activity boundary, and
iv) report how emissions due to the transport of the biomass residues used by the project activity have been accounted for.