Info Report Check
Submission incomplete:
1: The DOE is requested to explain how it verified the completeness of the data as per paragraph 373(a) of VVS-PA.
The monitoring plan requires the values of Vi,RG,m, VRG,m, MRG,m, vO2,EG,m, fcCH4,EG,m should be averaged on a minute basis. However, some data was missing in the spreadsheets. For example, on 6 Nov 2019, time stamp 7:56 is missing.

2: The DOE is requested to explain how it verified the determination of flare efficiency in line with the PDD and version 2 of tool “Project emissions from flaring”. The PDD and the tool require the determination of flare efficiency for each minute m.
However, the efficiency as shown in the each monthly spreadsheet is calculated each hour. It is also observed that the spreadsheets include a note “Flare efficiency in the hour h calculated when temperature of the exhaust gas of the flare (Tflare) is above 500 ºC for more than 40 minutes during the hour h” which is not in line with the version 2 of the tool. Refer to paragraph 373 (c) of VVS-PA.