Info Report Check
Submission incomplete:
1: Scope: The monitoring report does not contain the values of the monitored parameters. (EB 54 Annex 34)
Issue: i) The monitoring report does not indicate which are the specifications from the flare manufacturer (temperature, biogas flow rate) to adopt 90%, 50% or 0% for flare efficiency; ii) The revised monitoring plan states that the ratio (% EGy,diesel) will be calculated based on the electricity generated by the steam turbine and the electricity generated by diesel generator, however these values were not reported;

2: Scope: The verification report does not list each parameter required by the monitoring plan (VVM v.1.2 para 206)
Issue: i) The Verification Report mentions that "The flare manufacturer had provided PP with a document that specifies the method to determine the flare efficiency", however it is not clear how this document was verified as it is not listed in the Reference section of the Verification Report; ii) The Verification Report does not contain an assessment on how the electricity generated by the steam turbine and the electricity generated by diesel generator (used to determine the ratio (% EGy,diesel)) were verified.