Info Report Check
Submission incomplete:
1: Scope: The verification report does not state that the monitoring has been carried out in accordance with registered or the accepted revised monitoring plan. (VVS v2 para 235)
Issue: It appears that parameter of “Daily Mean Weight of baked HHK bricks (DMW hhk bricks,di)" has not been monitored on 28-31/08/2014 for all three Kilns.

2: Scope: The verification report does not provide findings and conclusions as to whether:
i)The project activity has been implemented and operated in accordance with the registered PDD or any approved revised PDD;
ii)The monitoring plan complies with the monitoring methodology and the actual monitoring complies with the monitoring plan, including compliance with any guidance provided by the Board regarding deviations from the provisions of a registered plan and/or methodology;
(iii) The data and calculation of GHG emission reductions have been assessed to correctly support the emission reductions being claimed.
(VVS v2 para 284(d))
Issue: Apparently parameter of “Daily Mean Weight of baked HHK bricks (DMW hhk bricks,di)" has not been monitored on 28-31/08/2014 for all three Kilns. Thus the DOE is requested to verify the accuracy of emission reduction due to the absense of this monitored data.