Info Report Check
Submission incomplete:
Scope: The verification and certification report does not describe the implementation status of the project as per VVS version 09.0 paragraph 385 (a).
Scope: The verification report does not describe the reasons for the phased-implementation delay and/or does not present the expected implementation dates as per VVS version 09.0 paragraph 385 (a).
Issue:
It is observed that:
(a) the added information of the main transformer (i.e. SF10-12500kVA/110kV, in page 6 of the revised PDD) indicate a smaller capacity than the installed capacity of the project activity (i.e. 20 MW);
(b) according to the registered PDD, the installed capacity of 20 MW was designed to supply electricity to the national grid.
The DOE shall provide further information on the user(s) of the generated electricity and clarify whether the national grid is the exclusive recipient of the power generated by the project activity.