(1). The monitoring report does not provide line diagram (graphical schemes) indicating all relevant monitoring points viz. for parameter EGEXP,y and EGIMP,y. The PP shall provide complete information related to the location of monitoring meters in the monitoring report. Please refer to “CDM project standard for project activities” version 1.0, paragraph 259.
(2). The ER sheet indicates that the electricity generated from each wind generator is monitored separately. However, it has been observed from the serial numbers of the meters as indicated on page 6 of the monitoring report that more than one wind generator is connected to each electricity meter. The DOE shall provide information on how it has verified the correctness and completeness of the reported monitoring system.