1: Scope: The verification report does not list each parameter required by the monitoring plan (VVM v.1.2 para 206)
Issue: Further verify how the distribution percentage at the Undale meter (Emission Reduction spreadsheet, 'Gen' sheet, column N) is in accordance with the monitoring plan. Please also confirm that the magnification factors have been applied correctly.

2: Scope: The verification report does not state how the DOE verified the information flow for the listed parameters. (VVM v.1.2 para 206)
Issue: Clarify how reading the meters at the end of the month is in compliance with the monitoring plan, considering that such readings should be done in the first week of each month as per the approved monitoring plan.