Scope: The verification report does not provide a conclusion on the verified amount of emission reductions achieved and/or determine that calculations of baseline emissions, project emissions and leakage as appropriate have been carried out in accordance with the formulae and methods described in the monitoring plan and the applied methodology document. (VVM v.1.2 para 208 (c) & 221 (h))
Issue: The DOE shall explain how it has verified that the project emission due to the produced steam are determined as per the method described in the monitoring plan (page 27 of the PDD) and applied ACM0012 version 6 (page 21), given that the quantity of steam supplied to the power plant, in stead of the the quantity of steam produced (MS,y), was monitored and used to calculate the project emission.