Submission incomplete:
1: Scope: The monitoring report does not contain a comparison of the actual CERs claimed in the monitoring period with the estimate in the PDD, and explanation on any significant increase, including all information (i.e. data or parameters) that is different from that stated in the registered PDD) as per PS version 09.0 paragraphs 256 and 257.
Issue: The DOE is requested to provide more information on the actual emission reductions in comparison with estimated emission reductions in the PDD, given the fact that only 50% of the installed capacity was in operation during the current monitoring period i.e. block 1 (363.3 MW) started operation from 04/01/2014 and block 2 (remaining 363.3 MW) from 24/03/2015, whereas 86.3% (1,739,449 tCO2e) of the estimated emission reductions (2,014,528 tCO2e) have been achieved in this monitoring period.
2: Scope: The verification and certification report does not determine if the assumptions used in emission calculations have been justified as per VVS version 09.0 paragraph 403 (d).
Issue: The DOE is requested to clarify the correctness of the GWP of methane (21 tCO2e/tCH4) used during the current monitoring period for emission reduction calculation in compliance with the "Standard for the application of the global warming potentials to clean development mechanism project activities and programme of activities for the second commitment period of the Kyoto Protocol", version 01.0 (EB69, Annex 3)
1: Scope: The monitoring report does not contain a comparison of the actual CERs claimed in the monitoring period with the estimate in the PDD, and explanation on any significant increase, including all information (i.e. data or parameters) that is different from that stated in the registered PDD) as per PS version 09.0 paragraphs 256 and 257.
Issue: The DOE is requested to provide more information on the actual emission reductions in comparison with estimated emission reductions in the PDD, given the fact that only 50% of the installed capacity was in operation during the current monitoring period i.e. block 1 (363.3 MW) started operation from 04/01/2014 and block 2 (remaining 363.3 MW) from 24/03/2015, whereas 86.3% (1,739,449 tCO2e) of the estimated emission reductions (2,014,528 tCO2e) have been achieved in this monitoring period.
2: Scope: The verification and certification report does not determine if the assumptions used in emission calculations have been justified as per VVS version 09.0 paragraph 403 (d).
Issue: The DOE is requested to clarify the correctness of the GWP of methane (21 tCO2e/tCH4) used during the current monitoring period for emission reduction calculation in compliance with the "Standard for the application of the global warming potentials to clean development mechanism project activities and programme of activities for the second commitment period of the Kyoto Protocol", version 01.0 (EB69, Annex 3)