1: Scope: The verification report does not state that the monitoring has been carried out in accordance with registered or the accepted revised monitoring plan. (VVM v.1.2 para 206 & 221(d))
Issue: The DOE shall clarify the change in the maximum flow rate of the flow meters (FT-503D, FT-503E, FT-001, FT-002, FT-003) reported in the monitoring report and validation report, in comparison to the values reported for the last monitoring period.

2: Scope: The verification report does not provide an assessment on whether the calibration of measuring equipments was conducted at a frequency specified in applied monitoring methodology or EB guidance if applicable, and/or the monitoring plan? (VVM v.1.2 para 184 (a) (ii) & EB 52 Annex 60)
Issue: The DOE shall clarify whether the calibration dates (for parameter VBdry gas,y, VA1,y, VA2,y, VA3,y, wcarbon dry gas,B,y and m condensate,B,y) cover the whole monitoring period starting from 01/05/2011 to 31/07/2011, given that the calibration dates (26/05/2011 and 05/07/2011) reported in the monitoring report do not cover the whole monitoring period.