Submission incomplete:
1: Scope: The verification report does not state that the monitoring has been carried out in accordance with registered or the accepted revised monitoring plan. (VVM v.1.2 para 206 & 221(d))
Issue: The approved monitoring plan does not provide for grid electricity to be by-passed through the bus line of the project activity. Clarify how the electricity that was diverted through the project activity (electricity not eligible for emission reductions) was separated from the electricity usually exported from the project activity (electricity eligible for emission reductions) .

2: Scope: The verification report does not provide an assessment on whether the calibration of measuring equipments was conducted at a frequency specified in applied monitoring methodology or EB guidance if applicable, and/or the monitoring plan? (VVM v.1.2 para 184 (a) (ii) & EB 52 Annex 60)
Issue: Calibration dates for M7, M8 and M9, as presented in the Verification Report, are inconsistent with the dates presented in the Monitoring Report.