1: Scope: The verification report does not state that the monitoring plan is in accordance with the applied methodology. (VVS v.3 para 232)
Issue: The DOE has not provided a statement whether the revised monitoring plan is in accordance with the approved methodology applied by the registered CDM project activity.

2: Scope: The verification report does not state that the monitoring has been carried out in accordance with registered or the accepted revised monitoring plan. (VVS v3 para 235)
Issue: The DOE is requested to further substantiate how the monitoring has been carried out in accordance with the revised monitoring plan as the new meter Feng 1 and new meter Feng 4 have accuracy class of 0.5, whereas the revised monitoring plan requires the accuracy of the electricity meters reaches 0.5s level above.