Submission incomplete:
Scope: The verification report does not provide an assessment of the compliance with EB 52 Annex 60 'Guidelines for assessing compliance with the calibration frequency requirements' for the calibration delay. (VVM v.1.2 para 184 (a) (ii) & EB 52 Annex 60)
Issue: the DOE shall clearly report the maximum permissible error applicable to: 1) ABB gas turbine meter from 1 Feb 2011 to 19 April 2011, 2) Siemens steam pressure meter from 1 Feb 2011 to 27 April 2011, and 3) Siemens steam temperature meter from 1 Feb 2011 to 17 April 2011 in line with footnote 2 of EB52 Annex 60. In doing so, the DOE shall also explain how the error was applied to the emission reductions calculation in the submitted spreadsheet in line with the applicable guideline.
Scope: The verification report does not provide an assessment of the compliance with EB 52 Annex 60 'Guidelines for assessing compliance with the calibration frequency requirements' for the calibration delay. (VVM v.1.2 para 184 (a) (ii) & EB 52 Annex 60)
Issue: the DOE shall clearly report the maximum permissible error applicable to: 1) ABB gas turbine meter from 1 Feb 2011 to 19 April 2011, 2) Siemens steam pressure meter from 1 Feb 2011 to 27 April 2011, and 3) Siemens steam temperature meter from 1 Feb 2011 to 17 April 2011 in line with footnote 2 of EB52 Annex 60. In doing so, the DOE shall also explain how the error was applied to the emission reductions calculation in the submitted spreadsheet in line with the applicable guideline.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: