Info Report Check
Submission incomplete:
1: Section D.3 of the submitted monitoring report states that the monitoring of the project activity doesn’t include sampling. However, as per the registered monitoring plan in the PDD page 59 and the monitoring report page 18, the Pn,i,y (Weight fraction of the waste type i in the sample n collected during the year y) and FCFi (Faction of fossil carbon in total carbon of waste type i) are to be monitored as per a sampling plan with the following requirements (in line with page 27 of AM0025, v.13.0.0): the size and frequency of sampling should be statistically significant with a maximum uncertainty range of 20% at a 95% confidence level.
The PP/DOE are requested to provide this sampling information and the verification opinion in the submitted documentation, in line with para. 261 of the VS-PA, v.03.0 and para. 362 of the VVS, v.03.0.


2: As per the Verification Report page 25 and the spreadsheet submitted TAG ¨Project Emissions¨ CELLS-G14to22, the values for FCFi are fixed while as per page 61 of the registered monitoring plan it must be measured by the project participants, where the size and frequency of the sampling should be statistically significant with a maximum uncertainty range of 20% at a 95% confidence level. The PP/DOE are requested to clarify how the monitoring of the FCFi complies with all the requirements as per the registered monitoring plan, as required by paras. 362 and 363 of the VVS, v.03.0 and paras. 261 and 260-c of the VS-PA, v.03.0.