Submission incomplete:
1: Scope: The monitoring report does not contain calculations of baseline emissions, project emissions, leakage (if any), and/or emission reductions, including reference to formulae and methods used. (EB48 - Annex 68 paragraph 10 (a) (vii))
Issue: The PP is requested to provide further information on the calculation of the baseline emissions as the monitoring report only includes the baseline emission factor calculation.

2: Scope: The verification report does not provide an assessment that all physical features of the proposed CDM project activity proposed in the registered PDD are in place and/or that the project participant has implemented and operated the proposed CDM project activity as per the registered PDD or the approved revised PDD. (VVM v.1.2 para 196)
Issue: The DOE is requested to further explain how the implementation of the CDM project activity has been done as per the registered PDD, as the DOE has not provided information about the installation of meter P6H48 (for measuring the "Auxiliary electricity consumed from the grid") which is not mentioned in the registered monitoring plan and previous monitoring periods.

3: Scope: The verification report does not provide an assessment of the compliance with EB 52 Annex 60 'Guidelines for assessing compliance with the calibration frequency requirements' for the calibration delay. (VVM v.1.2 para 184 (a) (ii) & EB 52 Annex 60)
Issue: The DOE is requested to provide: (a) a validation opinion on the absence of the calibration for meter IP6H48 in light of paragraph 4 to 8 of EB52 Annex 60; and (b) an assessment for the delayed calibration for the main and backup meters (calibrated on 23 April 2010, and subsequently on 26 April 2011) as per paragraph 4 of EB52 Annex 60.