Submission incomplete:
1: Scope: The verification report does not describe the implementation status of the project. (For project activities that consist of more than one site, the report shall clearly describe the status of implementation and starting date of operation for each site. For CDM project activities with phased implementation, the report shall state the progress of the proposed CDM project activity achieved in each phase under verification). (VVM v.1.2 para 198 (a)).
Issue 1: The facilities for supplying electricity to PICL have not yet been installed. Additional information is required on how the DOE verified that the installation of the facilities supplying electricity to PICL it is only delayed and it has not been canceled.
Issue 2: Rice husk is transferred from neighbor NLRM by trucks and not by conveyor belt as described in the registered PDD. Additional information is required on the implementation and operation status of the conveyor belt.

2: Scope: The verification report does not provide a conclusion on the verified amount of emission reductions achieved and/or determine that calculations of baseline emissions, project emissions and leakage as appropriate have been carried out in accordance with the formulae and methods described in the monitoring plan and the applied methodology document. (VVM v.1.2 para 208 (c) & 221 (h))
Issue: the Verification Report does not contain a clear statement that formula used for calculating project emission and leakage are in accordance with that in the approved methodology and the registered PDD.