Submission incomplete:
1: Scope: The monitoring report does not contain the values of the monitored parameters used to calculate baseline, project and leakage emissions as well as other parameters required by the applied methodology and the registered monitoring plan. (PS ver. 09 para 248 )
Issues: i. The registered MP (pg. 30) shows that monitored data for biomass consumed (Qsawdust,boiler and Qsawdust,thermic) will be crosschecked with the biomass procurement data. However, the monitoring report does not provide information on biomass procurement data, and the results of cross-checking; and ii. The VR (pg. 24) has reported that the total energy input was calculated based on fuel consumption and average NCV and comparing it with total energy generated by project equipments. However, the submitted monitoring report does not provide information on the cross-check with the energy balance and the results of the comparison. Please refer to the approved monitoring methodology (AMS-I.C ver 19 page 21).


2: Scope: The verification report does not indicate that the information provided in the monitoring report has been cross-checked with other sources such as plant log books, inventories, purchase records, laboratory analyses. (VVS v9, para 373 (b (iv)) and 403 (b)).
Issue: The VR (pg. 16) reports that the NCVsawdust was crosschecked. However, details of the crosschecking (e.g. how it was crosschecked, results of the crosschecking etc.) have not been provided.