Submission incomplete:
1: Scope: The monitoring report does not contain a description of the monitoring systems, quality assurance and/or quality control system employed by the project activity, data collection procedures (information flow including data generation, aggregation, recording, calculation and reporting), organizational structure, roles and responsibilities of personnel, emergency procedures for the monitoring system, and/or line diagrams showing all relevant monitoring points). (PS v1 para 190)
The PP/DOE has not reported the locations of exported electricity meter and imported electricity meter mentioned in the registered PDD.

2: Scope: The monitoring report does not contain a description of the equipment used to monitor each parameter including details on accuracy class and calibration information (frequency, dates of calibration and validity) as specified by the monitoring methodology and the monitoring plan. (PS v1, para 192 (b))
The PP/DOE is requested to justify how it has verified that the conservative approach has been applied for delayed calibratin , in doing so, please provide the date of actual date of calibration of imported electricity meter and the result of the calibration.