18:02 11 Jan 25
Info Report Check
Submission incomplete:
Scope: The verification report does not state that the monitoring has been carried out in accordance with registered or the accepted revised monitoring plan. (VVS v2 para 235)
Issue: The DOE is requested to clarify how it has verified the parameter ECLE,l,y, (net increase in electricity consumption of source l in year y as a result of leakage) in line with the approved revised monitoring plan (PDD version 02, dated 27/11/2013), given that the parameter is required to be measured continuously, whereas for the Corneche site, the parameter was calculated using a conservative approach due to a contingency in the power meter for July and August 2008 as stated in the VR, page 24. The DOE shall clarify how the approach used by the PP to calculate electricity consumption for Corneche site is in accordance with section 2.3 of Appendix 1 of the CDM Project Standard version 07.
Scope: The verification report does not state that the monitoring has been carried out in accordance with registered or the accepted revised monitoring plan. (VVS v2 para 235)
Issue: The DOE is requested to clarify how it has verified the parameter ECLE,l,y, (net increase in electricity consumption of source l in year y as a result of leakage) in line with the approved revised monitoring plan (PDD version 02, dated 27/11/2013), given that the parameter is required to be measured continuously, whereas for the Corneche site, the parameter was calculated using a conservative approach due to a contingency in the power meter for July and August 2008 as stated in the VR, page 24. The DOE shall clarify how the approach used by the PP to calculate electricity consumption for Corneche site is in accordance with section 2.3 of Appendix 1 of the CDM Project Standard version 07.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: