Info Report Check
Submission incomplete:
1: Scope: The monitoring report does not contain the values of the monitored parameters used to calculate baseline, project and leakage emissions as well as other parameters required by the applied methodology and the registered monitoring plan. (PS v1, para 191, 192 (a)(c )(d)(e)(f))
Issue: The monitoring plan (PDD page 28-29) indicates that the electricity generated by the project activity is calculated based on the monitoring of the net electricity measured at individual machine (M2) and the installed at 66 KV side (M3) as “The reading through Meter M3 is considered as the energy received by GETCO of the entire farm connected to that particular transformer.” However, the PP did not report readings of M2 and M3 and the values of the other WTG connected to the same main meter at the substation used for apportioning the net electricity generation of the project activity.

2: Scope: The spreadsheet does not contain all parameters required to be monitored and/or reported at the intervals required by the monitoring plan and the applied methodology?
Issue: The PP did not report the monthly values of meters M2 and M3, which are used to determine the electricity exported used for the apportioning approach.