Submission incomplete:
Scope: The verification report does not state that the monitoring has been carried out in accordance with registered or the accepted revised monitoring plan. (VVM v.1.2 para 206 & 221(d))
Issue: The monitoring report page 7 states that the net electricity output to the grid was monitored with M1and the project owner crosschecked it with M2 at the project site. This contradicts the approved monitoring plan (registered PDD page 27) which states that the reading of M2 will be monitored continuously and cross-checked with the reading of M1. In the spreadsheet, it is observed that the smallest of the two reading and the transaction receipt is used for the emission reduction calculations. Verification report does not indicate which of the two meter readings was used for the emission reduction calculations. The Project Participant and the DOE are requested to address this inconsistency, in particular, to make it clear how the amount of net electricity exported to the grid that is used for the emission reduction calculations was determined and if it is in line with the monitoring plan.