Submission incomplete:
1: Scope: The monitoring report does not contain a description of the monitoring systems, quality assurance and/or quality control system employed by the project activity, data collection procedures (information flow including data generation, aggregation, recording, calculation and reporting), organizational structure, roles and responsibilities of personnel, emergency procedures for the monitoring system, and/or line diagrams showing all relevant monitoring points). (PS v07 para 250)
Issue: The MR (p. 7) states that “the project has two collection lines and shares the same transmission line with other collection lines from other project of the same project owner”. The line diagram on MR (p. 5) and the registered PDD (p. 8) only show the particulars for the proposed project activity. The PP/DOE are requested to provide a complete line diagram which shows all the other power plants connected together with the proposed CDM project activity and relevant monitoring points.
2: Scope: The verification report does not provide a description of the actual operation of the project activity (VVS v7, para 273 (b))
Issue: The current monitoring period runs from 09/11/12 to 20/01/14 and all the generated electricity was supplied to the grid from 09/11/12. The VR (p.9) confirmed that all the generated electricity was delivered to the North China power grid (NCPG) based on the PPA dated 01/03/2013. The DOE (VR p. 13) further confirms that the wind farm issued sales receipts of the project covering the period from 09/11/12 to 20/01/14. It is noted that the sales receipts were issued from 09/11/12 which is before the date (01/03/2013) the grid connection agreement was signed. The DOE is requested to provide information on how the PP can issue the grid company with the sales receipts before the grid connection agreement was signed.
1: Scope: The monitoring report does not contain a description of the monitoring systems, quality assurance and/or quality control system employed by the project activity, data collection procedures (information flow including data generation, aggregation, recording, calculation and reporting), organizational structure, roles and responsibilities of personnel, emergency procedures for the monitoring system, and/or line diagrams showing all relevant monitoring points). (PS v07 para 250)
Issue: The MR (p. 7) states that “the project has two collection lines and shares the same transmission line with other collection lines from other project of the same project owner”. The line diagram on MR (p. 5) and the registered PDD (p. 8) only show the particulars for the proposed project activity. The PP/DOE are requested to provide a complete line diagram which shows all the other power plants connected together with the proposed CDM project activity and relevant monitoring points.
2: Scope: The verification report does not provide a description of the actual operation of the project activity (VVS v7, para 273 (b))
Issue: The current monitoring period runs from 09/11/12 to 20/01/14 and all the generated electricity was supplied to the grid from 09/11/12. The VR (p.9) confirmed that all the generated electricity was delivered to the North China power grid (NCPG) based on the PPA dated 01/03/2013. The DOE (VR p. 13) further confirms that the wind farm issued sales receipts of the project covering the period from 09/11/12 to 20/01/14. It is noted that the sales receipts were issued from 09/11/12 which is before the date (01/03/2013) the grid connection agreement was signed. The DOE is requested to provide information on how the PP can issue the grid company with the sales receipts before the grid connection agreement was signed.