Submission incomplete:
The monitoring report (page 9) indicates that the check meter for Dhom SHP is out of plant premises whereas the DOE (VR, page 8) verifies that the check meter is installed at the project premises. The PP/DOE are requested to provide further information on the location of the main and check meters of Kasari SHP and Dhom SHP by providing clear line diagrams (graphical schemes) which show all relevant monitoring points for each sub-buddle (Kasari SHP & Dhom SHP). Please refer to the PS-PA ver. 03 paragraph 258.
The monitoring report (page 9) indicates that the check meter for Dhom SHP is out of plant premises whereas the DOE (VR, page 8) verifies that the check meter is installed at the project premises. The PP/DOE are requested to provide further information on the location of the main and check meters of Kasari SHP and Dhom SHP by providing clear line diagrams (graphical schemes) which show all relevant monitoring points for each sub-buddle (Kasari SHP & Dhom SHP). Please refer to the PS-PA ver. 03 paragraph 258.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: