00:47 05 Jul 25
Info Report Check
Submission incomplete:
Scope: The spreadsheet does not contain the formulae of calculation that are shown in the spreadsheet cells whenever possible. (EB48 - Annex 68 paragraph 10 (b) (ii)).
Issue: According to the monitoring report (page 23 and 24), measurement of NCSG and VSG in the time period from 10/06/2010 to 01/07/2010 has been outside valid AST status, thus a conservative manner (by applying the maximum permissible error of the instruments) had been followed on the NCSG and VSG measurements during this period. The Verification Report (page 20) also states that "The delay from annual calibration period second AST test were reflected by application of maximum permissible error of the instruments for NCSG (2.69%)and VSG (3.22% combined uncertainty for normalized stack flow) as it is required by EB 52 annex 60 for the period from 10 June 2010 till 1 July 2010 (end of this monitoring period)". However, this calculation process was not demonstrated in the submitted CER calculation spreadsheet. Given the impact of these parameters on the CERs, please transparently present the calculation process.
Scope: The spreadsheet does not contain the formulae of calculation that are shown in the spreadsheet cells whenever possible. (EB48 - Annex 68 paragraph 10 (b) (ii)).
Issue: According to the monitoring report (page 23 and 24), measurement of NCSG and VSG in the time period from 10/06/2010 to 01/07/2010 has been outside valid AST status, thus a conservative manner (by applying the maximum permissible error of the instruments) had been followed on the NCSG and VSG measurements during this period. The Verification Report (page 20) also states that "The delay from annual calibration period second AST test were reflected by application of maximum permissible error of the instruments for NCSG (2.69%)and VSG (3.22% combined uncertainty for normalized stack flow) as it is required by EB 52 annex 60 for the period from 10 June 2010 till 1 July 2010 (end of this monitoring period)". However, this calculation process was not demonstrated in the submitted CER calculation spreadsheet. Given the impact of these parameters on the CERs, please transparently present the calculation process.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: