Info Report Check
Submission incomplete:
1: Scope: The monitoring report does not contain the implementation status of the project (including a brief description of the installed technology and/or equipments, relevant dates of project activity e.g. date of construction, commissioning, continued operation periods, etc.) during the monitoring period under consideration. (EB48 - Annex 68 paragraph 10 (a) (i) & EB 54 Annex 34).
Issue: The PP/DOE are requested to report and verify when the plant started operating at the current plant capacity of 830-850 tHNO3/day.

2: Scope: The verification report does not determine if the assumptions used in emission calculations have been justified and/or emission factors, default values and other reference values have been correctly applied. (VVM v.1.2 para 208 (d) & (e))
Issue: The PP/DOE are requested to report how the baseline emission factor (EFBL) was calculated as it appears that a lower value of baseline nitric acid production, NAPBC, (145,637 tHNO3) was considered instead of the actual total NAPBC of 160, 124 tHNO3 which was established during the baseline campaign.