Info Report Check
Submission incomplete:
1: Scope: The spreadsheet does not contain all parameters required to be monitored and/or reported at the intervals required by the monitoring plan and the applied methodology?
Issue: In some cells there are imbedded formulas, which are not explained. Specifically, for the months of April, May and June the generated electricity and the imported electricity from the turbines owned by Panama Business Center (see cells L4, M4, Q4, R4, V4 and W4 of worksheet "Generation Detail") have been adjusted by +/-0.2%. Also for the month of August, the generated electricity and the imported electricity from the turbine owned by Power Link System private Limited (see cells AF22 and AG22 of worksheet "Generation Detail") have been adjusted by +/-0.5%.

2: Scope: The spreadsheet does not contain explanation with regard to application of formulae in the spreadsheet. (EB48 - Annex 68 paragraph 10 (b) (iii)).
Issue: As per comment under 2.1, it is not clear why some values in the cells have been modified. Explanations are needed. Further detailed information is required on: What are the meters having a delayed calibration; what are these meters for (Exp.? or Imp.); what maximum accuracy level has been applied for these different type of meter (0.5/0.2, 15%?) to export and import.