Info Report Check
Submission incomplete:
1: Scope: The spreadsheet does not contain the formulae of calculation that are shown in the spreadsheet cells whenever possible. (EB48 - Annex 68 paragraph 10 (b) (ii)).
Issue: The formulae for Gross Electricity Exported (Column H) values is missing.

2: Scope: The verification report does not provide a conclusion on the verified amount of emission reductions achieved and/or determine that calculations of baseline emissions, project emissions and leakage as appropriate have been carried out in accordance with the formulae and methods described in the monitoring plan and the applied methodology document. (VVM v.1.2 para 208 (c) & 221 (h))
Issue: The DOE is asked to clarify how delayed calibration of grid electricity export/import meter has been accounted for throughout the period from 02/04/11 to 31/07/11 in the emission reduction calculation spreadsheet.