Info Report Check
Submission incomplete:
1: Scope: The validation report does not contain a confirmation that the corrected information is accurate reflection of actual project information as per VVS version 09.0 paragraph 304.
Issue: The proposed corrections under the PRC include the update of the version of the methodology to the latest version. The DOE is requested to explain how this change can be considered under correction. Paragraph 275 of the CDM project standard (version 09.0) indicates that corrections are intended to make any corrections to project information or parameters fixed at validation.
Please note that the CDM project standard (version 09.0) considers application of a later version of the methodology under permanent changes to the registered monitoring plan, and that the CDM project standard for project activities (version 01.0) considers voluntary update of the applied methodology to a later valid version of the methodology under changes to project design.
2: Scope: The monitoring report does not contain the implementation status of the project (including a brief description of the installed technology and/or equipments, relevant dates of project activity e.g. date of construction, commissioning, continued operation periods, etc.) during the monitoring period under consideration as per PS version 09.0 paragraph 244.
Issue: Page 2 of the monitoring report reports the installation of 22 wind turbines, while page 6 of the monitoring report indicates 61 wind turbines. Please clarify.
1: Scope: The validation report does not contain a confirmation that the corrected information is accurate reflection of actual project information as per VVS version 09.0 paragraph 304.
Issue: The proposed corrections under the PRC include the update of the version of the methodology to the latest version. The DOE is requested to explain how this change can be considered under correction. Paragraph 275 of the CDM project standard (version 09.0) indicates that corrections are intended to make any corrections to project information or parameters fixed at validation.
Please note that the CDM project standard (version 09.0) considers application of a later version of the methodology under permanent changes to the registered monitoring plan, and that the CDM project standard for project activities (version 01.0) considers voluntary update of the applied methodology to a later valid version of the methodology under changes to project design.
2: Scope: The monitoring report does not contain the implementation status of the project (including a brief description of the installed technology and/or equipments, relevant dates of project activity e.g. date of construction, commissioning, continued operation periods, etc.) during the monitoring period under consideration as per PS version 09.0 paragraph 244.
Issue: Page 2 of the monitoring report reports the installation of 22 wind turbines, while page 6 of the monitoring report indicates 61 wind turbines. Please clarify.