Submission incomplete:
VVS-PA Para 357:
The DOE is requested to explain how it verified the compliance of the monitoring plan with the applied methodology. In particular:
(a) As per the applied methodology ACM0002, EGPJ,y refers to the quantity of net electricity generation that is produced and fed into the grid. However, in the project activity EGPJ,y refers to project plant/unit for captive purpose in year y. In doing so, the DOE is requested to explain: (i) whether there is electricity generated by the project activity that is supplied to the grid; (ii) whether the electricity to the HZL mining complex is supplied directly from the project activity or wheeled through the grid;
(b) As per the TOOL05 - Baseline, project and/or leakage emissions from electricity consumption and monitoring of electricity generation to which the methodology refers to for monitoring of parameter EGPJ,y, the electricity generation (gross or net) shall be cross-checked with records of electricity sale (e.g. sales receipt). However, such provision is not included in the monitoring plan and there is no information regarding any cross-check with records of electricity sale.
VVS-PA Para 357:
The DOE is requested to explain how it verified the compliance of the monitoring plan with the applied methodology. In particular:
(a) As per the applied methodology ACM0002, EGPJ,y refers to the quantity of net electricity generation that is produced and fed into the grid. However, in the project activity EGPJ,y refers to project plant/unit for captive purpose in year y. In doing so, the DOE is requested to explain: (i) whether there is electricity generated by the project activity that is supplied to the grid; (ii) whether the electricity to the HZL mining complex is supplied directly from the project activity or wheeled through the grid;
(b) As per the TOOL05 - Baseline, project and/or leakage emissions from electricity consumption and monitoring of electricity generation to which the methodology refers to for monitoring of parameter EGPJ,y, the electricity generation (gross or net) shall be cross-checked with records of electricity sale (e.g. sales receipt). However, such provision is not included in the monitoring plan and there is no information regarding any cross-check with records of electricity sale.