Submission incomplete:
The project participants shall describe the monitoring system and provide line diagrams (graphical schemes) showing all relevant monitoring points (PS-PA ver.01 paragraph 259).
The verification report (Section E.3) mentions that a line diagram showing the relevant metering points is provided in Section C of the MR. However, the line diagram (showing the relevant monitoring points) has not been provided on the MR.
The project participants shall describe the monitoring system and provide line diagrams (graphical schemes) showing all relevant monitoring points (PS-PA ver.01 paragraph 259).
The verification report (Section E.3) mentions that a line diagram showing the relevant metering points is provided in Section C of the MR. However, the line diagram (showing the relevant monitoring points) has not been provided on the MR.