Submission incomplete:
1: The DOE shall provide information on how it has verified the completeness of the line diagrams of the monitoring system, given the fact that the relevant monitoring points of parameter QHNO3,cons,y is not observed in the diagram in page 5 of the monitoring report. In doing so, the monitoring report shall provide line diagrams (graphical schemes) showing all relevant monitoring points. Please refer to “CDM project standard for project activities” version 1.0, paragraph 259.


2: The DOE shall clarify on how it has concluded that the calibrations are conducted at the frequency as specified by the methodology and the monitoring plan (i.e. page 23 of the validation report), given the fact that delay calibration is observed. For example, one of the flow meters (i.e. FT760CD) used to monitor QHNO3,cons,y was recently calibrated on 05/04/2016 and 29/06/2017 (page 34 of the monitoring report) whereas the monitoring plan requires annual calibration.